BM522 Project Management – CW1 Individual Project Report: The Regent House Hotel Digital Guest Check-In Project
| University | Buckinghamshire New University (Level 5, C23 framework) |
| Module | BM522 Project Management |
| Assessment | CW1 – 1,500-word individual project report |
| Weighting | 50% |
| Deadline | Saturday 14 November 2026, before 2:00 pm |
| AI status | Non-secure: reasonable and appropriate AI use permitted |
BM522 CW1 gives students a ready-made project and a full activity list, then asks them to plan it like a project manager: business case and SMART objectives, a network diagram with the critical path, a Gantt chart, stakeholders, a WBS, a risk register and quality criteria.
Project Scenario (summary)
The Regent House Hotel is a privately owned 85-room boutique hotel in Belfast serving business travellers and weekend tourists. Manual paper registration, identity checks, payment verification and key allocation cause long queues between 3 pm and 6 pm on Fridays, Saturdays and event dates. Management has approved a digital guest check-in and check-out system with pre-arrival registration, secure ID upload, payment confirmation, digital or kiosk room access, self-service check-out and automated receipts. Scope includes platform procurement and configuration, integration with the Property Management System, kiosks or tablets, staff training, a GDPR and data security review, pilot testing and full rollout.
- Start: Monday 11 January 2027; full rollout before the summer season, within six months
- Indicative budget: £180,000; minimum disruption to hotel operations
- Key risks: integration issues, staff resistance, guest data privacy, supplier delays, cybersecurity and front-office disruption
- Team: general manager, front-office manager, IT support, finance manager, data protection officer, external software supplier, reception staff representatives and pilot guest users
Activity Scheduling Information
| ID | Task | Days | Predecessors |
| 1 | Approve project mandate and appoint project manager | 2 | – |
| 2 | Review current front-office process and identify requirements | 7 | 1 |
| 3 | Prepare business case and project initiation document | 5 | 2 |
| 4 | Obtain approval from hotel senior management | 2 | 3 |
| 5 | Prepare supplier specification and request for proposal | 4 | 4 |
| 6 | Invite suppliers and receive proposals | 10 | 5 |
| 7 | Evaluate proposals, select supplier and negotiate contract | 8 | 6 |
| 8 | Complete contract approval and procurement sign-off | 3 | 7 |
| 9 | Conduct technical assessment of existing hotel systems | 5 | 4 |
| 10 | Design digital check-in process and guest journey | 6 | 4 |
| 11 | Configure digital check-in software | 10 | 8, 9, 10 |
| 12 | Integrate system with existing Property Management System | 8 | 11 |
| 13 | Complete GDPR, data security and payment compliance review | 6 | 11 |
| 14 | Install guest self-service kiosks and/or tablet devices | 6 | 8, 9 |
| 15 | Conduct internal testing and resolve technical issues | 10 | 12, 13, 14 |
| 16 | Develop operating procedures and train front-office staff | 7 | 10, 15 |
| 17 | Run pilot launch, review feedback and implement improvements | 12 | 16 |
| 18 | Full system rollout and project closure report | 4 | 17 |
All durations are working days (Monday–Friday, eight hours per day; weekends excluded, public holidays ignored). Network diagram calculations use the day 0 convention.
Coursework Tasks
- Task 1 – Business case, project objectives and methodology [15 marks]: business need and aim, three SMART objectives, deliverables, milestones, outcomes and benefits, time/cost/operational constraints, and a briefly justified planning approach.
- Task 2 – Network diagram, critical path and Gantt chart [25 marks]: (i) a network diagram showing all activities, dependencies, durations, ES, LS, EF and LF, with the critical path highlighted and the shortest completion time stated; (ii) a Gantt chart in MS Project or an approved tool showing sequence, dependencies, dates and milestones.
- Task 3 – Stakeholder analysis and communication strategies [20 marks]: at least five internal and external stakeholders on a power/interest matrix, their expectations, concerns, influence and likely conflicts, plus a communication plan in the appendix.
- Task 4 – Work Breakdown Structure [10 marks]: a clearly numbered, deliverable-oriented WBS (not a chronological activity list).
- Task 5 – Risk analysis: a risk register with mitigation strategies for the five highest-priority risks.
- Task 6 – Quality: five quality requirements with acceptance criteria, specifications and control measures.